Erect six each 18-60™ panels
in a circular shape around the
feeder. The opening for the eight
foot wide MINE™ gate should
face the natural direction hogs
travel to the bait site. Each panel
is 16 feet long with an eight inch
overlap. Posts should be driven in
the center of each overlap.
The left diagram illustrates the
proper order to drive posts. Place
the solar charger on #23, camera
on #24 and booster antenna pole
on #25 outside the enclosure so
these devices are not damaged
when hogs are captured. Posts
should be driven every four feet
for maximum strength.
Ensure all T-post lugs face inward to secure the panels from lifting up.
Posts should be driven in the center of each eight inch panel overlap and
driven in line of a vertical support on single panels. Each post should
secure the panel with at least four M.I.N.E.™ Post Clips. The diagrams
below show the proper anchor points needed for maximum strength.
.