wiki:mine_trap:installation:panels [2015/05/25 08:57] |
wiki:mine_trap:installation:panels [2021/12/15 12:07] (current) |
||
---|---|---|---|
Line 1: | Line 1: | ||
+ | ~~DISCUSSION: | ||
+ | ===== INSTALLING 18-60™ PANELS & POSTS ===== | ||
+ | {{ : | ||
+ | in a circular shape around the | ||
+ | feeder. The opening for the eight | ||
+ | foot wide MINE™ gate should | ||
+ | face the natural direction hogs | ||
+ | travel to the bait site. Each panel | ||
+ | is 16 feet long with an eight inch | ||
+ | overlap. Posts should be driven in | ||
+ | the center of each overlap. | ||
+ | ---- | ||
+ | {{: | ||
+ | proper order to drive posts. Place | ||
+ | the solar charger on #23, camera | ||
+ | on #24 and booster antenna pole | ||
+ | on #25 outside the enclosure so | ||
+ | these devices are not damaged | ||
+ | when hogs are captured. Posts | ||
+ | should be driven every four feet | ||
+ | for maximum strength. | ||
+ | ---- | ||
+ | Ensure all T-post lugs face inward to secure the panels from lifting up. | ||
+ | Posts should be driven in the center of each eight inch panel overlap and | ||
+ | driven in line of a vertical support on single panels. Each post should | ||
+ | secure the panel with at least four M.I.N.E.™ Post Clips. The diagrams | ||
+ | below show the proper anchor points needed for maximum strength. | ||
+ | < | ||
+ | <br> | ||
+ | </ | ||
+ | {{: | ||
+ | ---- | ||
+ | ---- | ||
+ | |||
+ | {{backlinks> |