 +~~DISCUSSION:off~~
 +===== INSTALLING 18-60™ PANELS & POSTS ===== 
  
 +{{ :wiki:mine_trap:installation:install-panels-1.png?nolink&200|}}Erect six each 18-60™ panels 
 +in a circular shape around the 
 +feeder. The opening for the eight 
 +foot wide MINE™ gate should 
 +face the natural direction hogs 
 +travel to the bait site. Each panel 
 +is 16 feet long with an eight inch 
 +overlap. Posts should be driven in 
 +the center of each overlap. 
 +----
 +{{:wiki:mine_trap:installation:install-panels-2.png?nolink&200 |}}The left diagram illustrates the 
 +proper order to drive posts. Place 
 +the solar charger on #23, camera 
 +on #24 and booster antenna pole 
 +on #25 outside the enclosure so 
 +these devices are not damaged 
 +when hogs are captured. Posts 
 +should be driven every four feet 
 +for maximum strength.
 +---- 
 +Ensure all T-post lugs face inward to secure the panels from lifting up. 
 +Posts should be driven in the center of each eight inch panel overlap and 
 +driven in line of a vertical support on single panels. Each post should 
 +secure the panel with at least four M.I.N.E.™ Post Clips. The diagrams 
 +below show the proper anchor points needed for maximum strength.
 +<html>
 +<br>
 +</html>
 +{{:wiki:mine_trap:installation:install-panels-3.png?nolink&250 |}}{{:wiki:mine_trap:installation:install-panels-5.png?nolink&75 |}}{{:wiki:mine_trap:installation:install-panels-4.png?nolink&150 |}}{{:wiki:mine_trap:installation:install-panels-6.png?nolink&52 |}}
 +----
 +----
 +
 +{{backlinks>.}}